Based on the mission of Jordan Islamic Bank to lead in the field of renewable energy, the project was developed to cover 85% of its branches’ consumption in the capital Amman and in the cities of Madaba, Zarqa, and Salt via a “wheeling” program with JEPCO.
The project comprised the installation of 8,352 modules rated 325W by JA Solar and 52 string inverters by ABB and mounting system by Schletter.
As time was of the essence, the project was delivered and installed within a record time of less than 120 days to serve the client’s mandate.