Based on the client’s vision to lead in the field of renewable energy, the Jordan Islamic Bank project was developed to cover 85% of the consumption of its branches in Amman, Madaba, Zarqa and Salt cities via a “wheeling” program with JEPCO.
This project involved the installation of 8,352 modules, rated 325W by JA Solar, and 52 string inverters by ABB and mounting system by Schletter.
Since time was of the essence, this project was delivered and installed within a record time of less than 120 days to serve the client’s mandate.