Project Facts

Project Type
Roof Top
Project capacity
1.1MWp
Launch Date
March 2017
Completion Date
September, 2018
Steel Structure size
3000 s.q.m.

This project for Sayegh Group comprised the joint design and construction of a new Steel Structure facility sized +3000s.q.m. by maani steel, a subsidiary of maani ventures. It also included the construction of a Solar PV plant of over 12,000s.q.m. utilizing existing and new roof tops, by maani solar.

The project entailed the challenge of utilizing different roof tops with varying tilts and azimuths that was later delivered with an optimum design to achieve the highest possible return per kWp installed.

The 1.1MWp plant now covers 100% of the factory’s consumption by generating over 1.7GWh annually and saving over 1020 Tons of carbon dioxide per year in line with the client’s ethos to lead in the field of manufacturing whilst protecting the environment.